Contents
Paulo Afonso Hydroelectric Complex
The Paulo Afonso Hydroelectric Complex (Complexo Hidrelétrico de Paulo Afonso), also known as the Paulo Afonso Complex, is a system of three dams and five hydroelectric power plants on the São Francisco River near the city of Paulo Afonso in Bahia, Brazil. The complex exploits an 80 m natural gap on the river, known as the Paulo Afonso Falls. Constructed in succession between 1948 and 1979, the dams support the Paulo Afonso I, II, III, IV and Apollonius Sales (Moxotó) power plants which contain a total of 23 generators with an installed capacity of 4,279.6 MW. PA I was the first large power plant constructed in Brazil and the complex constitutes the densest area of dams in Brazil. The complex provides electricity to areas in northeastern Brazil and is the main tourist attraction in the region.
Background and history
On January 23, 1913, the 1.1 MW Angiquinho Hydroelectric Plant, built by industrialist Delmiro Gouveia, was the first use of the Paulo Afonso Falls for power production and the first hydroelectric power plant in northeastern Brazil. Construction of the power plant was intended to spur economic growth in the area and soon after another hydroelectric plant was constructed upstream near Petrolândia. By the 1940s Brazil's Ministry of Agriculture recognized the importance of harnessing the São Francisco River for economic development in the semi-arid region. They began to plan the river's development and the Companhia Hidro-Elétrica do São Francisco (CHESF) was formed in 1945. On May 23, 1944, construction on Paulo Afonso I had been authorized with two generators. Construction began in 1948; workers and engineers experienced difficulty diverting the river, transporting the turbines to the site while in midst of dangerous work conditions. Tunnels and a cavern had to be excavated for Brazil's first underground power plant. Due to the depth and strength of the river near the falls, it was not diverted until 1954. On January 15, 1955, Brazilian President João Café Filho inaugurated PA I. Previously, in 1953, CHESF negotiated with the government for a third generating unit at PA I and the excavation of another underground power plant for the future PA II adjacent to PA I on the falls. The third generator at PA I was commissioned on September 18, 1955, and construction of PA II began that year as well. By 1961, PA II was complete and on October 24 that year, its first generator was commissioned. PA II's five other generators became operational between 1962 and December 18, 1967. Construction on PA III started soon after in 1967 and was complete in 1971 with its first generator commissioned on October 21 that year. Another generator was commissioned in 1972 and the final two in 1974, the last of which on August 5. In 1971, construction had moved to the Apollonius Sales (Moxotó) Dam and power plant 4 km upstream from the falls. In 1977, construction was completed and its four generators went online in April of that year. In 1972, construction began on the final dam and power plant, PA IV, 2 km southwest of the falls. Construction was complete in 1979 and its first generator commissioned on December 1. Two more generators were commissioned in 1980, two in 1981 and the final on May 28, 1983. Construction of the dams caused a loss of 1600 ha of land along with displacing 52,000 people.
Specifications
Apolônio Sales (Moxotó)
The Apolônio Sales Dam and power plant were originally known as Moxotó but were renamed after Apolônio Sales, the founder of CHESF. The dam is a 30 m high, 2825 m long rock and earth-fill embankment dam. The dam creates a 1200000000 m3 capacity reservoir with a surface area of 100 km2 and catchment area of 630000 km2. The dam and its reservoir are primarily intended to regulate water flow to PA I, II and III 4 km downstream. On the dam's west side, it supports a 20 floodgate spillway with a 28000 m3/s capacity. The power plant is located on the east side of the dam near the reservoir's shore and contains four generators, each with Kaplan turbines. Each generator has a nameplate capacity of 100 MW for a total installed capacity of 400 MW.
Paulo Afonso I, II, III
Situated directly on top of the Paulo Afonso Falls, the Delmiro Gouveia Dam supports Paulo Afonso I, II and III. The dam is 20 m high, 4,707 m long and is a concrete gravity type. The reservoir formed by the dam has a 26000000 m3 capacity and surface area of 4.8 km2. The dam has one uncontrolled spillway and a controlled spillway on its outer linings while also supporting four controlled spillways on the front of the falls. These four surface spillways when open, discharge water below and essentially recreate the falls. All three power plants are about 82 m underground and adjacent to one another. PA I lies in the center and is housed in a 60 m long, 31 m high and 15 m wide cavern. It contains three 60 MW generators with Francis turbines, for an installed capacity of 180 MW. The generators are Vertical Sync-type and were manufactured by Westinghouse. The turbines were manufactured by Dominion Engineering Works. PA II is a 104 m long, 36 m high and 18 m wide power house. It contains six Vertical Sync-type generators with Francis turbines. Two of the generators are 70 MW, one is 75 MW and the remaining three are 176 MW, for a total installing capacity of 443 MW MW. The generators were manufactured by S. Morgan Smith and Hitachi while the turbines by Voith. PA III's power house is 127 m long, 46 m high and 18 m wide. It contains four 198.55 MW Vertical Sync-type generators manufactured by Siemens for an installed capacity of 795.2 MW. Each generator utilizes a Francis turbine manufactured by Voith.
Paulo Afonso IV
The Paulo Afonso Dam located 2 km southwest of the falls is 35 m high and 7430 m long. The dam is an earth and rock-fill type but is 1053 m in length of concrete structures which include the power plant's intake and the spillway. The spillway is composed of eight floodgates and has a maximum discharge capacity of 10000 m3/s. The dam withholds a 127500000 m3 capacity reservoir with a surface area of 12.9 km. The reservoir receives water through a channel that originates near the southern end of the Appolonius Sales Reservoir and continues south, skirting the city. The PA IV power house is also underground and is 210 m long, 52 m high and 24 m wide. It contains six 410.4 MW MW generators for an installed capacity of 2462.4 MW. Each generator is a SíncronoVertical-type manufactured by Siemens and utilizes vertical shaft Francis turbines that were manufactured by Voith.
This article is derived from Wikipedia and licensed under CC BY-SA 4.0. View the original article.
Wikipedia® is a registered trademark of the
Wikimedia Foundation, Inc.
Bliptext is not
affiliated with or endorsed by Wikipedia or the
Wikimedia Foundation.